Sprinklers

What is a sprinkler riser?

A sprinkler riser is the vertical pipe that carries water up from the control valve set to the sprinkler pipework above, and in everyday use the name covers the whole assembly at its base: stop valve, alarm valve, gauges, and test and drain valves.

BS EN 12845LPC Rules 2 November 2026 6 min read by Sentry Sprinkler Protection

Book a free survey or ring 07927 555475

Sprinkler alarm valve set and riser on a wall in a room under fit-out
Sprinkler alarm valve set and riser on a wall in a room under fit-out. One of ours.

A fire sprinkler riser is the vertical pipe that takes water from the control valve set up to the sprinkler pipework on the floors above. In conversation the word usually means more than the pipe: it means the whole assembly at the bottom of it, the valves, gauges and alarm trim that every sprinkler installation is controlled from. Sentry Sprinkler Protection inspects and services these assemblies on every sprinkler visit, and this guide explains what each part does and what a building owner should expect to see.

The pipe and the assembly

BS EN 12845 defines a riser narrowly, as a vertical distribution pipe feeding a distribution or range pipe above (clause 3.52 in the LPC Rules 2015 book). That is the pipe itself.

When a facilities manager or an engineer says “the sprinkler riser”, though, they nearly always mean the riser together with its control valve set: the assembly where the water supply enters the installation and from which the riser climbs. Every installation must have one, made to EN 12259-2 for wet systems or EN 12259-3 for dry ones (clause 15.1). It is the heart of the system, because it is where the water is turned on and off and where the alarm is raised when a sprinkler operates.

A riser sprinkler system, then, is simply a sprinkler installation fed through a riser: the supply comes in at the bottom, passes the control valve set, and rises to the pipework serving each floor.

What you will find on a sprinkler riser

Stand in front of one and you will see the same few parts, in roughly this order from the bottom up.

PartWhat it doesWhere the rule is
Main stop valveTurns the water to the installation on and off. Must close clockwise, show open or shut, and be strapped and padlocked openBS EN 12845, 15.2
B gaugeShows the supply pressure, immediately before the control valve set15.7.3 a)
Alarm valveLifts when water flows to an open sprinkler and sends water to the alarm15.1
C gaugeShows the pressure held in the installation, immediately after the valve set15.7.3 b)
Alarm test valveA 15 mm valve that lets water through to prove the alarm without opening a sprinkler15.5.1
Drain valveEmpties the installation for maintenance, with its outlet no more than 3 m above the floor15.4

On a dry installation the alarm valve holds air above it rather than water, and its B gauge must also have a pointer that records the highest pressure reached (15.7.3). The types of sprinkler system page explains why some areas are dry.

The alarm itself is raised in one of two ways: water through the valve turns a water motor gong on the outside wall, or it trips a flow or pressure switch wired to the building’s fire alarm. Our guide on how a sprinkler system works follows the water from the sprinkler back to that alarm.

Where the riser is, and why access matters

The riser sits where the supply enters the protected area: a sprinkler valve room, a plant room, or a riser cupboard, usually on the ground floor and usually signed on the door.

Three things about that room matter more than they look:

  • It must stay above freezing. The LPC Rules check the valve room temperature every week (TB203.2.3), because a frozen valve set is a system that cannot operate.
  • It must stay clear. The fire service and your contractor both need to reach the valves quickly. A riser cupboard that has become a store room slows everyone down.
  • It must stay locked to strangers but open to you. Somebody on site should hold the key and know where the room is.

What gets checked, and how often

Under the LPC Rules, which carry the BS EN 12845 routines with the FPA’s technical bulletins, the riser is the first thing looked at on every visit.

Every week (TB203.2.2), the routine includes:

  • reading and recording the B and C gauges (TB203.2.2.2 a);
  • confirming the stop valves are locked open (TB203.2.2.2 c);
  • opening the alarm test valve and checking the alarm bell rings for 30 seconds and any pressure switch operates (TB203.2.2.3).

A free weekly test log sets those out in order, with space for the readings.

At the service visits the valve set is looked at in much more depth, and at the annual service it is stripped and inspected rather than simply tested. That difference matters on a quotation: “inspected” and “stripped” are not the same job. Our sprinkler servicing intervals guide sets out what each visit adds.

The faults we find on risers

Most riser faults are small, and most are found by someone simply looking.

  • A valve left shut after maintenance, or half shut, with no strap and padlock. This is the one that matters most, because the system looks normal and will not work.
  • Gauge readings drifting from what they were last month. A falling C gauge on a wet system points to a leak; a falling B gauge points to the supply.
  • An alarm valve that passes, letting a trickle through that keeps a jockey pump running or the alarm chattering.
  • A pressure switch or flow switch that no longer reports, so a sprinkler could operate without the alarm ever telling anyone.
  • A dry valve room that gets cold in winter because a heater has failed.

Every one of those is a repair rather than a replacement, and most can usually be put right on the same visit. Where the riser needs alterations because the building has changed, that is a design question; our sprinkler installation team handles extensions and upgrades.

A sprinkler riser is not a dry or wet riser

The names collide, and it causes real confusion on site.

A sprinkler riser feeds the automatic sprinklers and is charged all the time, so the system operates on its own when a sprinkler opens.

A dry riser or wet riser is a firefighting main for the fire service to connect hoses to on each floor, designed to BS 9990. A dry riser is empty until the fire service pumps water into it; a wet riser is kept full by its own pumps. Our guide to wet and dry risers explains the difference between those two.

A building can have both kinds, sometimes in the same shaft, and each has its own test regime.

Residential sprinkler systems

Sprinklers in blocks of flats are designed to BS 9251, a different standard from BS EN 12845, and the valve arrangements differ with it. What this guide says about clauses and weekly checks applies to commercial BS EN 12845 installations. Our guide to sprinklers in blocks of flats covers the residential side.

What to do next

If you are responsible for a building with a sprinkler system, three things are worth doing this week: find the riser, check every valve on it is strapped and padlocked open, and look at the last few weeks of gauge readings. If any of those is harder than it should be, sprinkler servicing from Sentry Sprinkler Protection puts the riser on a routine and records it properly, with a certificate and a photographed defect list after every visit.

This work, on our sites

Questions we get asked

Is a sprinkler riser the same thing as a dry riser?

No. A sprinkler riser feeds the automatic sprinklers and is full of water, or of air on a dry system, all the time, ready to operate on its own. A dry riser is an empty firefighting main that the fire service charges from an inlet outside when they arrive. They are designed to different standards: BS EN 12845 for sprinklers, BS 9990 for dry and wet risers.

Where is the sprinkler riser in a building?

At the point where the water supply enters the protected area: a sprinkler valve room, a plant room, or a riser cupboard on the ground floor. It is usually signed on the door. If nobody on site can find it, that is worth fixing before anything else, because the fire service and your contractor both need to reach it quickly.

What do the two pressure gauges on a sprinkler riser show?

The B gauge sits just before the control valve set and shows the pressure of the water supply. The C gauge sits just after it and shows the pressure held in the installation. Under BS EN 12845 both are read and written down every week, and a change from the usual figures is the first sign of a supply problem or a leak.

Should the main valve on a sprinkler riser be locked?

Yes, locked open. BS EN 12845 requires every stop valve that could cut off the water to the sprinklers to show whether it is open or shut and to be secured with a strap and padlock or equivalent. A shut valve leaves the system looking normal while it cannot deliver water.

Where this comes from

British Standards are copyright documents and most are bought rather than read free. We hold the ones we work to. If you need to know what one of them says about your building, ask us rather than buying it.

Read next BS 9990 explained: what a dry riser owes, and when A dry riser needs a visual inspection every six months and a full pressure test every twelve months, charged to 12 bar and held for 15 minutes, with a certificate issued against BS 9990.

When is your next visit due?

Pick the system and the month a contractor last came. You will see each routine, the date it falls due and anything that is already late.

Weekly checks are your own team's, logged on site. Our free weekly test log covers them on one page.

1 · The system

2 · The last contractor visit

Pick a month and a year to see your dates.

  • Every 3 months Quarterly test Water moving through the system proved to raise the alarm
  • Every 6 months Half-yearly service The interim contractor service
  • Every 12 months Annual service The full service, with the pump proved under flow
  • BS EN 12845

Counted from the visit you picked. If that was not the annual service, the annual may fall sooner. Your insurer or fire strategy can ask for more.

Book the visit or ring 07927 555475

Tell us the building. We will tell you what it is due.

No survey fee to find out where you stand. Describe the site and we will tell you which intervals apply and what the visit involves.

Based
37 Dickens Drive, Kettering, NN16 9EG
Covering
Kettering · Corby · Wellingborough · Northampton · Rushden · Daventry · Market Harborough · Bedford and England, from our base in Kettering
Office hours
Monday to Friday, 7am to 5pm. Emergency line any hour.

What do you need?
Type of building optional
Who do we come back to?

    If it is urgent, ring rather than write. We are on the phone Monday to Friday, 7am to 5pm, and outside those hours the same number reaches the emergency line.

    Or send it straight to us

    Or just ring 07927 555475 and talk it through. Mon to Fri, 7am to 5pm. Emergencies any hour.